ENA Connect Direct: A Step-by-Step Guide for Solar Installers
- to use, provided by the UK's network operators
- Free
- to use, provided by the UK's network operators
- installing: every application is pre-installation
- Before
- installing: every application is pre-installation
- for a decision when every automated check passes
- Minutes
- for a decision when every automated check passes
- devices on its live register on 9 Nov 2026
- 9,743
- devices on its live register on 9 Nov 2026
The short answer
ENA Connect Direct (connect-direct.energynetworks.org) is the free national portal the UK's network operators run with the Energy Networks Association for domestic low-carbon technology: solar PV, batteries, EV chargers and heat pumps on existing homes. You register your company, apply before you install, and an application that passes every automated check is approved in real time; the rest go to the DNO. After installing you send the commissioning form through the same portal. It also holds the device register that replaced the ENA Type Test Register. Commercial jobs don't go through it: for non-domestic installations, Connect Direct says to use the G98, G99 and G100 forms.
If you fit solar on homes as well as businesses, Connect Direct is where the domestic paperwork now starts. If you only do commercial roofs, you still need it, because its device register is where you find an inverter's reference for a G98 or G99 form.
Everything below is from Connect Direct's own pages and the ENA's connection guide, read on 9 November 2026. Connect Direct is still being developed, so check its FAQs for changes.
On this page
What ENA Connect Direct is
Connect Direct describes itself as a national platform developed by the UK's Distribution Network Operators in partnership with the Energy Networks Association (ENA). It replaces the paper forms for domestic low-carbon technology (LCT) connections with one online process that is the same for every application you send to a GB or Northern Ireland network operator and most IDNOs.
It has three groups of users:
- Installers apply for approval before fitting solar PV, batteries, EV charge points or heat pumps to an existing home, and send the commissioning information afterwards.
- Manufacturers register their devices with the ENA, get them assessed and make them available for installers to pick.
- Customers don't use it themselves, but get written confirmation of approval to install.
It costs nothing: Connect Direct's FAQ says the network operators provide it free of charge.
Which applications go through Connect Direct
The short version: domestic, before installation. What Connect Direct and the ENA guide say for each kind of job:
| The job | Where it goes | What the source says |
|---|---|---|
| Solar PV, a battery, an EV charger or a heat pump on an existing home | Connect Direct, before you install | Connect Direct says an application is needed every time one of these goes on an existing property, and all its applications are pre-installation. |
| Several of those at the same home | One Connect Direct application | Its FAQ says to submit a single application containing every low-carbon technology going in at the property. |
| A non-domestic site: a shop, farm, factory or office roof | The G98, G99 and G100 forms | Connect Direct's installer section says to use the forms for non-domestic installations. |
| A more complex domestic connection | The DNO's usual application process | The ENA guide says Connect Direct is aimed at smaller devices in homes and that, for now, more complex applications should follow the legacy process. |
| Several installations in the same area | Paper G98 forms, or multiple applications through the Connect Direct API | The ENA guide gives both options. |
| A job you haven't been instructed on yet | Not allowed | Connect Direct cannot be used for speculative applications. |
The ENA guide adds that installers who can use Connect Direct may still use the paper-based process instead, and that for a domestic G99-sized system, Connect Direct can be used as an alternative way to submit the application. Our guide to the G99 application covers the forms route.
How to register your company on Connect Direct
- 1
Create an account and sign in
Use Sign Up / Log In on connect-direct.energynetworks.org. Use your company email address: accounts link to your company by its email domain.
- 2
Register your company (first person only)
Pick "Register Company" during set-up and follow the steps. Whoever registers the company becomes its Company Administrator.
- 3
Add your team
Colleagues sign up with the same company email domain and are linked automatically, but the Company Administrator must approve each one. Without company email addresses, they need an invitation from the administrator.
- 4
Set up multi-factor authentication
Download an authenticator app such as Google or Microsoft Authenticator, scan the QR code on the MFA screen and enter the code it shows. An administrator in your organisation can reset someone's MFA.
As Company Administrator you can invite team members, approve new users and see every application your team submits. Connect Direct has a short video on its home page that walks through first-time registration.
How to submit a Connect Direct application, step by step
Connect Direct asks you to have these to hand:
- The installation property's postcode or site location.
- The customer's personal details. Connect Direct uses them to email the customer once you're approved.
- Your company details.
- The installation details.
- The make and model of each device, which you pick from the device register.
- The MPAN (Meter Point Administration Number), if the address can't be found.
- Supporting information, such as a photo of the cut-out.
- 1
Gather the details
Postcode or site location, customer details, your company details, installation details, the device make and model, the MPAN if the address isn't found, and a photo of the cut-out.
- 2
Start the application before you install
Every Connect Direct application is made pre-installation. Put every low-carbon technology going in at the property into one application.
- 3
Pick each device from the register
Choose the make and model from Connect Direct's device register, which holds the products manufacturers have registered with the ENA.
- 4
Let the decision engine assess it
It checks the cut-out and supply equipment, supply capacity, looped supplies, whether a network upgrade is needed, maximum demand, equipment compliance and the DNO's approval thresholds.
- 5
Approved, or escalated to the DNO
If every check passes, the application is approved automatically in real time. If not, it goes to the DNO for review, and updates come back through Connect Direct.
- 6
Install, then submit the commissioning form
Once approved, complete the commissioning form from the My Applications tab (or through the API if you're integrated).
Who is responsible for the data? Anyone instructed to install the technology can submit, including an installer acting for the customer, but Connect Direct says it remains the connecting customer's responsibility that the correct data goes in. In practice that means you: check the MPAN, the cut-out photo and the device model before you press submit.
How Connect Direct assesses an application
A data-driven decision engine checks, among other things:
- the safety of the cut-out and supply equipment;
- whether the supply capacity is sufficient;
- whether the property is on a looped supply;
- whether a network upgrade is needed;
- whether the property's maximum demand is within the DNO's thresholds;
- equipment compliance, and whether the equipment is within the DNO's approval thresholds.
Pass every check and it is approved automatically in real time. Fail one and it is escalated to the DNO for review. Each DNO sets its own auto-approval thresholds, and they can vary from area to area, so the same system can sail through in one place and go to review in another. Give it a clear cut-out photo and pick devices that show as Compliant on the register.
The Connect Direct device register
Connect Direct's Live Device Register is headed "Search the ENA Type Test Register". The ENA closed its old Type Test Register on 16 April 2024 and moved all its data to Connect Direct, and devices registered before Connect Direct launched in May 2024 were migrated across. On 9 November 2026 it listed 9,743 devices, each with a System Reference, a compliance status, the manufacturer, model, category, type, capacity in kW and phase.
How to search it, what each status means and what to do when a product isn't there are in our guide to the ENA Type Test Register.
Connect Direct vs the G98 and G99 forms
For a commercial solar installer the split is simple:
- Domestic jobs: apply on Connect Direct before you install, then commission there.
- Non-domestic jobs: use the forms. A small, Fully Type Tested system at one premises is a G98 notification (Form B) within 28 days of commissioning; anything bigger is a G99 application before installation, with a G100 form if export is limited.
- Either way: look the inverter and battery up on the device register. On a G99 form, a Fully Type Tested unit's reference is all the ENA guide says you need to show compliance.
Not sure which network operator a site is on? The first two digits of the MPAN tell you; see our DNO application guide.
Submitting through the Connect Direct API
Connect Direct offers installers and software providers an API to submit applications to the DNOs and receive updates. Pick "Software Provider" when you register and you get OpenAPI-standard documentation, a sandbox for testing and access to the support portal, where you raise a ticket for sandbox and production API keys. The ENA guide notes the API is one way to make multiple applications in the same area.
Getting help with Connect Direct
Log in and raise a ticket in the Connect Direct Support Portal, or email connectdirect@energynetworks.org. If you can't get past multi-factor authentication, ask your company's administrator to reset it from their User Management Portal.
The paperwork is the easy part once you're doing the work. If finding commercial jobs is the harder part, Solar Surveys UK books qualified commercial solar survey appointments with business owners. You only pay for appointments that are actually attended; see how to get commercial solar leads for every channel compared.
ENA Connect Direct: FAQ
What is ENA Connect Direct?
A national platform built by the UK's Distribution Network Operators with the Energy Networks Association. Installers use it to get approval before fitting low-carbon technology (solar PV, batteries, EV charge points and heat pumps) to existing homes, with one process for every GB and Northern Ireland network operator and most IDNOs. Manufacturers use it to register their devices.
Is ENA Connect Direct free?
Yes. Connect Direct's FAQ says it is provided free of charge by the UK Distribution Network Operators.
Can I use ENA Connect Direct for commercial solar?
No. Connect Direct is for domestic low-carbon technology, and its installer section says to use the G98, G99 and G100 forms for non-domestic installations. A commercial roof goes to the DNO as a G99 application, or a G98 notification if it is small enough.
Do I apply on Connect Direct before or after installing?
Before. All Connect Direct applications must be submitted pre-installation. After installing, you complete the commissioning form from the My Applications tab.
How long does a Connect Direct application take?
If every automated check passes, the application is approved in real time and Connect Direct says a decision is given in minutes. If any check fails, it is escalated to the DNO for review, which takes longer. Each DNO sets its own auto-approval thresholds, and they can vary by area.
How do I log in to ENA Connect Direct?
Use Sign Up / Log In on connect-direct.energynetworks.org, then enter the code from your authenticator app (multi-factor authentication). If you can't get in, an administrator in your company can reset your MFA, or you can email connectdirect@energynetworks.org.
Who can submit a Connect Direct application?
Anyone instructed to install an EV charger, heat pump or domestic generation, including an installer acting for the customer. Connect Direct says it remains the connecting customer's responsibility that the right data is submitted.
Does Connect Direct replace the ENA Type Test Register?
Yes. The register closed on 16 April 2024 and its devices were migrated to Connect Direct, which now publishes them in its Live Device Register. It also replaced the ENA's EV charger and heat pump spreadsheets.
Can software or a CRM submit Connect Direct applications?
Yes. Pick "Software Provider" when you register to get the OpenAPI documentation and a sandbox, then raise a ticket in the support portal for sandbox and production API keys.
How do I contact ENA Connect Direct?
Log in and raise a ticket through the Connect Direct Support Portal, or email connectdirect@energynetworks.org.
Sources
Checked 9 Nov 2026. Connect Direct is still being developed and each DNO sets its own thresholds, so check the current pages before relying on them.
- ENA Connect Direct: home page (for installers, manufacturers and customers, and FAQs)
- ENA Connect Direct: Learn More & FAQs (getting set up, MFA, connection applications, commissioning)
- ENA Connect Direct: Live Device Register ("Search the ENA Type Test Register")
- Energy Networks Association, Distributed Generation Connection Guide: G98 & G99, March 2025 (copy published by SSEN)
- Energy Networks Association: G98, G99 and G100 forms (linked from Connect Direct for non-domestic installations)
Related guides
- ENA Type Test Register
How to look up an inverter or battery on the ENA database, and what to do if it isn't listed.
- G98 form and notification
Form B field by field, the 16A-per-phase limit and the 28-day deadline.
- G99 application
Who submits it, the forms, the stages, fees and timescales.
- G99 application checklist
Every G99 step on one printable page.
- G100 export limitation
Export limiting schemes, compliant devices and the forms.
- DNO application for solar
Find the DNO from the MPAN and pick the right route.
- Competent person schemes for solar
Which scheme covers PV, self-certification and how it sits with MCS.
- MCS database and MID
Registering jobs, the MID login and the MCS lookups.
- Commercial solar survey checklist
What to capture on site, including the supply and the cut-out.
- Commercial solar leads
Booked survey appointments with business owners.
- All installer guides
Every guide for UK solar installers in one place.
Browse commercial solar leads free
Qualified survey appointments with business owners near you. Pay only per attended appointment. No pitch, no pay.