Commercial Solar Site Survey Checklist: 18 Checks in 3 Stages

A commercial solar survey has three phases: confirm the decision-maker, roof ownership and energy data before you travel; capture roof, electrical and access details on site; and follow up with a proposal within 48 hours. Installers who run every survey through a fixed checklist convert significantly more appointments into signed contracts.

Before the visit

The survey is won or lost before you arrive. A wasted trip to a site where the decision-maker doesn't show is the most expensive outcome in commercial solar. Confirm these first:

  • Confirm the decision-maker will attend, not a site manager with no authority
  • Verify roof ownership or landlord consent in writing
  • Request 12 months of half-hourly electricity consumption data
  • Check the site's grid connection capacity and any existing export agreements
  • Review roof age, material and any planned re-roofing works
  • Confirm the business's VAT status and financing preference (CAPEX vs PPA)

On site

Capture everything you need to quote without a return visit:

  • Measure usable roof area and record orientation and pitch
  • Photograph shading sources: parapets, plant, trees, neighbouring buildings
  • Inspect roof structure and note any asbestos or access constraints
  • Locate the main intake, distribution boards and available spare ways
  • Check for three-phase supply and meter arrangement
  • Record scaffolding, access and welfare requirements for installation
  • Walk the cable route from array to intake and measure run lengths

If the DNO is likely to cap what the site can send to the grid, note it now: a G100 export limitation scheme often gets a larger system connected without a reinforcement bill. Almost every commercial roof also needs a G99 application form in before install, so take the MPAN, the supply type and photos of the main board while you are there, and check which solar panel distributors near the site hold the inverter you plan to specify.

After the survey

Commercial solar deals typically close in 4 to 8 weeks. Speed and structure in the follow-up matter more than the survey itself:

  • Send the proposal within 48 hours while the conversation is warm
  • Include generation estimate, payback period and 25-year cashflow
  • Present both CAPEX and financed options side by side
  • Book the follow-up call before you leave the site
  • Log every objection: most commercial deals close on the second or third touch

For the payback figure in the proposal, the free commercial solar payback calculator works it out from the site, the system size and the half-hourly data you collected.

Skip the qualification phase entirely

Every lead on Solar Surveys UK arrives with the first phase already done: decision-maker confirmed by phone, roof ownership verified, and the appointment booked. And if the customer doesn't sit down for the survey, you don't pay. See live commercial solar leads or check what leads cost.

Pre-qualified surveys, booked for you

Browse live UK commercial solar opportunities. Free for 7 days, no credit card required.

Start your free trial