GUIDE · FOR UK SOLAR INSTALLERS AND SALES TEAMS · 10 MIN READ
How to Sell Commercial Solar: From Booked Survey to Signed Contract
The short answer
Commercial solar sales go to the installer who makes the decision easy for everyone who signs. Survey with the decision-maker present, build the proposal on real energy data, show your workings, raise the lease, roof and G99 early, and follow up against an agreed decision date. The opportunity you start with matters as much as how you sell it.
For UK solar installers and their sales teams: the commercial solar sales process stage by stage, the proposal, objections, follow-up and the mistakes that lose deals.
The commercial solar sales process
Selling solar to a business means more people, more data, a grid connection and usually a formal approval. Commercial deals on Solar Surveys UK typically close in 4 to 8 weeks from first contact, and each stage below is a place a deal can stall.
- 1
First call
Confirm what the business wants, who signs, roughly what it spends on electricity, whether it owns the building and when it could decide. Book the survey with the decision-maker.
- 2
Site survey
Roof, structure, supply, point of connection, shading and consumption, plus a conversation with whoever signs. It is a sales meeting as much as a technical one.
- 3
Proposal
A system designed around the site's real energy data, with the financial case set out so the finance director can check it.
- 4
Finance
Outright purchase, asset finance, leasing or a power purchase agreement, depending on the customer's cash and appetite for owning the asset.
- 5
Board or FD sign-off
Someone other than the person you met often approves the spend, so the proposal has to work when forwarded without you.
- 6
Grid connection (G99)
Nearly every commercial system needs a G99 application. Start it early so the connection offer lands alongside the decision.
- 7
Contract
Final design, terms, payment stages, installation window and what happens if the connection offer changes the scope.
The stages overlap: start the grid conversation at the survey and put finance in the first proposal, so the customer never waits on you.
Preparing for the survey
The survey is your most important sales meeting. Before you travel:
- Confirm who will be there, and that it includes the person who signs.
- Ask for bills or half-hourly data in advance to sense-check the system size.
- Check whether the business owns or leases the building.
- Check the roof on satellite imagery: material, rooflights, shading.
- Find the likely network operator.
- Know which finance options you can offer.
On site, capture everything you need to write the proposal without going back to the customer. Our commercial solar survey checklist lists what to confirm before, during and after the visit.
Who's in the room and what they care about
Several people usually have a say, each with a different question. The proposal has to answer all of them, because it is passed around after you leave.
| Who | What they care about | What to bring |
|---|---|---|
| Managing director or owner | The overall case, risk, disruption and whether you will be around for the warranty. | A one-page summary, your track record and an install plan that works around operations. |
| Finance director | Cash flow, the payback method, assumptions, finance terms and how this ranks against other projects. | The workings behind every number, the energy data used and finance options side by side. |
| Facilities or operations manager | Roof access, safety, maintenance, monitoring and keeping the site running during the install. | A maintenance and monitoring plan and a realistic installation window. |
| Landlord (if the business leases) | Roof warranties, structural loading, who owns the system and what happens at lease end. | Structural information, the consent you need and a plan for lease end. |
Ask early who else approves it. If it goes to a board, find out when it meets and what format it wants. A proposal written for the board can be forwarded without rewriting.
Building the commercial solar proposal
It will be read by people who check numbers for a living, so credibility beats a headline figure. Include:
- A plain-English summary page: system size, what it does for the site, the investment and finance options.
- The energy data used (half-hourly data or bills) and the period it covers.
- The design: layout, inverters, any battery, and why it is sized that way.
- Estimated generation and how it was modelled, with the assumptions written down.
- Self-consumption versus export, including any export limit.
- The financial case with the method shown: tariff assumed, how payback was worked out and what changes it.
- Finance options side by side.
- The grid connection position: G99 status and what the connection offer could change.
- Warranties, maintenance, monitoring and insurance.
- Next steps and the dates that matter.
On payback, show the method, not just the answer. The tariff, when the site uses power, how much generation it uses itself and what it exports all change the result. A finance director who can follow and adjust your workings will trust them; one who finds an unexplained number will doubt the rest.
On finance, some customers want to buy outright, others prefer asset finance or a lease to spread the cost, and some only consider a power purchase agreement, where a third party owns the system and the business buys the electricity. More than one option keeps the conversation going when the answer is "we don't have the capital".
Objections and honest answers
Most objections are real business concerns, not stalling. Answer them honestly, with the customer's own information.
"Our roof isn't in great condition."
Treat it as a real issue. If the roof has less life left than the system, say so and price the options: repairs or overcladding first, another roof, a ground mount or a carport. A roof that fails under a new array costs you the reference as well as the job.
"We lease the building, so we'd need the landlord's consent."
Ask about the lease at the first call, not after the proposal: how long is left, who the landlord is, whether alterations are allowed. Offer what the landlord will want to see and suggest a three-way meeting early. A landlord who hears about it last is the slowest landlord.
"It's not in this year's budget."
Find out when the budget is set and by whom, then work back from that date. Finance can turn a capital spend into a monthly one. If the honest answer is next year, agree when to revisit. Don't discount to force it into this year.
"We'll wait for prices to drop."
Don't argue about where prices are going; nobody knows. Show the cost of waiting from their own bills: every month without the system is a month buying that electricity at today's tariff. Let them weigh that against any saving they expect.
"What if the grid won't take it?"
Explain G99 plainly: an application before installation, and a connection offer that may bring an export limit or reinforcement costs. A site that uses most of what it generates may suit an export limit. Make the contract conditional on an acceptable offer.
For the grid connection in detail (G98 vs G99, the forms, the DNO steps, export limitation and timescales) see our guide to the G99 application for commercial solar.
Follow-up after the survey
Deals are won or lost in the weeks after the survey. Each follow-up should give the customer something useful, not just ask if they have decided.
| When | What to do |
|---|---|
| Same day as the survey | Confirm what you agreed, list anything still missing (half-hourly data, the lease, roof drawings) and say when the proposal will arrive. |
| Proposal delivery | Present it live, with every signatory you can get. Don't just email a PDF. |
| A few days later | Ask what questions came up internally. This is where the FD's objections surface. |
| As the G99 response arrives | Update the proposal with the connection position. |
| Before the decision date | Agree when the board or FD will decide and what they still need. If it slips, agree a new date. |
| If it goes quiet | Ask whether the project is live, on hold or off. A clear no frees your time. |
Log every contact, question and agreed next step in your CRM; with several people involved, the deal often goes to whoever remembers what each asked for.
Mistakes that lose commercial deals
- Surveying without the person who signs, so you sell twice.
- Proposals built on guessed consumption.
- Overselling the financial case: one optimistic assumption undermines the rest.
- Raising the lease, the roof or the grid connection after the proposal.
- Emailing a proposal and waiting.
- Offering only one way to pay.
- No agreed decision date.
- Giving every enquiry the same time, whether or not anyone there can sign.
How lead quality changes your close rate
No sales process closes a site where nobody can sign, the business doesn't control the roof or there is no real interest, and each one costs a survey day. Your close rate depends on how many surveys start with the basics in place:
- The decision-maker is confirmed and at the survey.
- Roof ownership is known before you travel.
- Energy consumption is known, so the size is roughly right.
- There is genuine intent, not just curiosity.
That is how Solar Surveys UK qualifies every lead: generated in-house by TNW Marketing's paid media, then qualified by phone by a UK-based team who confirm the decision-maker, roof ownership, energy consumption and intent. You see the system size, property type and how many installers have registered interest before you commit. It's pay per appointment, priced by system size (see how much commercial solar leads cost), and no sit, no pay: if the customer doesn't sit for the survey, you don't pay.
A booked survey gets you in the room. Winning the contract is still down to the survey, the proposal and the follow-up above.
To compare where commercial work can come from, read how to get commercial solar leads. For booked surveys vs form fills, see solar leads UK, and for what we list, see commercial solar leads or how solar survey leads work. Regional pages cover Manchester, London and Birmingham.
Commercial solar sales: FAQ
How long does a commercial solar sale take?
It varies with job size, who signs and the grid connection. On Solar Surveys UK, commercial deals typically close in 4 to 8 weeks from first contact; board approvals, landlord consent or a slow connection offer can take longer.
Who should be at a commercial solar survey?
Whoever signs, ideally with someone who speaks for the budget, plus the person who looks after the building. If the business leases, find out early who the landlord is.
What should a commercial solar proposal include?
A plain-English summary, the energy data used, the design, generation and its assumptions, self-consumption and export, the financial case with its method, finance options, the grid position, warranties and next steps.
Should I quote a payback period in my proposal?
Show how you worked it out, not just a headline figure: tariff, generation, self-consumption and export. Finance directors check the method.
How do I answer "we'll wait for prices to drop"?
Don't predict prices. Use their own bills to show what each month of waiting costs at today's tariff.
What if the business doesn't own its building?
A tenant usually needs the landlord's consent. Ask about the lease at the first call and set out what happens to the system at lease end.
Does G99 affect the sale?
Yes. Almost every commercial system needs a G99 application, and the offer can bring an export limit or reinforcement costs. Raise it at the survey and start early.
How does lead quality affect my close rate?
A survey with the decision-maker confirmed, roof ownership checked and consumption known up front is a sales conversation, not a fact-finding visit.
Related guides
- All commercial solar lead guides
Every guide for UK installers buying commercial solar leads.
- Commercial solar survey checklist
What to confirm before, during and after the site visit.
- G99 application for commercial solar
G98 vs G99, forms, DNO steps, export limits and timescales.
- How to get commercial solar leads
Nine channels compared, and how to judge any lead provider.
- Solar leads UK: booked surveys, not form fills
What separates a good solar lead from an expensive one.
- How much do commercial solar leads cost?
Pricing by system size, the maths on a lead and a buyer's checklist.
- How solar survey leads work
What a solar survey is and how Solar Surveys UK works.
- Commercial solar leads in Manchester
Survey leads across Greater Manchester and the North West.
- Commercial solar leads in London
Survey leads across London and the South East.
- Commercial solar leads in Birmingham
Survey leads across Birmingham and the West Midlands.
- MCS certification for solar installers
How to get and keep MCS: standards, certification bodies, consumer codes, costs.
- G98 explained for installers
The 16A-per-phase limit, notify vs apply, the forms, and when you need G99.
- DNO application for solar
Find your DNO, pick the right route (G98, G99, G100) and get connected.
- Solar design software for UK installers
Easy-PV, OpenSolar, PV*SOL, PVsyst, Aurora and more, compared for UK work.
- UK solar wholesalers and distributors
Trade suppliers of panels, inverters, batteries and mounting, and how to choose one.
- MIS 3002 explained for solar PV installers
The MCS solar PV standard: scope, performance estimates, design, commissioning and handover.
- How to become a solar installer in the UK
Qualifications, training routes, MCS and the step to running your own solar business.
- SEO for solar companies
How UK installers win commercial solar enquiries from Google: pages, Google Business Profile, reviews, links and what it really takes.
- Solar advertising: Google and Facebook ads
Running Google, Meta and LinkedIn ads for commercial solar enquiries: targeting, landing pages, ad rules and what it really takes.
- Solar partnerships and referrals
Winning commercial solar work through energy brokers, landlords, contractors and customer referrals, and what it really takes.
- UK solar lead companies compared
Eight suppliers side by side: lead type, pricing, contracts and commercial vs residential.
Start with surveys worth selling to — free for 7 days
Browse real UK commercial solar survey opportunities in your area, with the decision-maker confirmed. Pay per appointment, no sit, no pay, and no credit card required to start.
Start your free trial