G99 Application for Commercial Solar: An Installer's Guide
The short answer
Almost every commercial solar job in Great Britain needs a G99 application. G98 only covers Fully Type Tested generation of up to 16A per phase at a premises (3.68kW single-phase, 11.04kW three-phase); anything bigger falls under Engineering Recommendation G99. That means applying to the network operator (DNO or IDNO) before you install, accepting a connection offer, then commissioning and, for most commercial (Type A) systems, sending the Installation Document within 28 days. The data from your site survey decides how smoothly it goes.
Every rule and figure below comes from the official ENA and DNO sources listed at the end.
G98 vs G99 at a glance
Both are Energy Networks Association (ENA) Engineering Recommendations: G98 for generation under 16A per phase, G99 for everything else.
| EREC G98 | EREC G99 | |
|---|---|---|
| What it covers | Fully Type Tested micro-generation of no more than 16A per phase in total at a premises: 3.68kW single-phase or 11.04kW three-phase. | All other generation. Type A is 0.8kW to under 1MW (below 110kV); Types B to D are 1MW and up. |
| When you deal with the DNO | Single premises: fit, then notify within 28 days of commissioning. Multiple premises nearby need approval first. | Apply before installing. The DNO assesses the network and issues a connection offer. |
| Main forms | Installation Document (Form B). | Type A: simplified form (A1-1) or standard application form; A2 compliance forms if needed; Installation Document (A3-1). |
| Witness testing | Not needed, per NGED. | Possible; the connection offer says so. |
| Commercial jobs | Rarely. | Almost always. |
When a commercial job needs G99
The 16A-per-phase line is the test: 11.04kW combined on a three-phase supply, so nearly any commercial roof is a G99 job. Batteries count too — NGED's guidance treats storage as generation when it exports.
The G99 Type sets the compliance work:
- Type A — 0.8kW to under 1MW, below 110kV. Most commercial roofs.
- Type B — 1MW to under 10MW. Adds a Power Generating Module Document (PGMD) and a Final Operational Notification.
- Types C and D — 10MW and above, or a connection at 110kV or more.
For inverter-connected solar, the Type is set by the total of all inverters behind one connection point: NGED's example of three 500kW PV inverters makes 1.5MW, so Type B. Units added to an existing G99 installation count with what's there; units added to an older G59 installation count separately.
The G99 fast track (Forms A1-2, A3-2, A3-3) tops out at 60A per phase with export capped at 32A by a G100 scheme, per SSEN and NGED — below most commercial jobs.
Which network operator handles it
Usually the regional DNO, but sometimes an Independent Distribution Network Operator (IDNO), which typically builds networks for new developments such as business parks. The ENA guide says the IDNO process is almost identical.
To check, take the first two digits of the site's MPAN from the bill: 10 is UK Power Networks (Eastern England), 15 Northern Powergrid, 16 Electricity North West, and so on in the ENA's table. No meter? Ask the DNO whose area you think the site is in.
The G99 application, step by step
The Type A route from the ENA's March 2025 connection guide. DNOs have their own forms and portals, so check with yours.
- 1
Talk to the DNO early
The ENA guide says to discuss plans with the DNO before starting work, as early as possible. Use its capacity maps and surgeries. A budget estimate, or a paid feasibility study, can flag reinforcement before the customer commits.
- 2
Decide who builds the connection
The DNO does non-contestable work on its existing network. Contestable work, such as new infrastructure, can go to an Independent Connections Provider (ICP) for a competing quote.
- 3
Apply before installing
Below 50kW three-phase (17kW single-phase) there is a simplified form in Annex A.1 of EREC G99; larger systems use the ENA standard application form, which all DNOs use. The ENA guide expects the installer to submit it for the customer.
- 4
Prove the equipment complies
For Fully Type Tested inverters registered on the ENA's Connect Direct portal, quote the Product ID. Otherwise send a Compliance Verification Report (Forms A2-1 to A2-3) before arranging commissioning.
- 5
Accept the connection offer
It sets out the works, any reinforcement, whether the connection is constrained, the costs and any witness testing. It is open for a set period, typically 30 to 90 days, and can be withdrawn if the project stalls.
- 6
Sign the agreements
Typically a Connection Agreement, an Adoption Agreement if an ICP was used, and an operating agreement for the interface. Some must be in place before construction.
- 7
Commission and notify
Test to section 15 of EREC G99. If the DNO is witnessing, send the scope, time and date at least 15 days before. Submit the Installation Document (A3-1), plus Form A2-4 if on-site compliance tests were needed, within 28 days of commissioning.
NGED says it normally witnesses some commissioning tests where a site's total capacity exceeds 50kW, and charges for witness tests.
What to gather before you apply
The fuller the application, the more accurate the quote and the faster the assessment. From what SSEN and NGED ask for, plus what you need to size the system, have ready:
- Site address, MPAN(s), and a letter of authority if the applicant isn't the landowner or occupier (SSEN asks for one).
- A site boundary plan and a layout plan with the point of supply marked.
- The supply: single- or three-phase, low or high voltage.
- Existing generation or storage on site — it can change the G99 Type.
- The proposed system: inverter make, model and rating, total capacity, any battery.
- Inverter Product IDs from Connect Direct, or the manufacturer's compliance information.
- Full export or a limit, and where a limiting device would go.
- The site's consumption pattern, to size the system and any export limit.
- When the customer wants to be connected.
Nearly all of this comes from the site visit, which is why a proper commercial solar survey matters: miss the supply, the point of connection or the consumption data and you're back to the customer for it. Our commercial solar survey checklist covers what to capture.
Export limitation and G100
Export limitation caps what a site sends to the grid, and any scheme must comply with EREC G100.
Full export isn't always available. Where a connection would breach equipment ratings or statutory limits, the ENA guide says the DNO may reinforce the network, or offer a restricted connection such as a maximum export level, which a customer can also ask for. DNOs must also consider curtailable connections, restricted until reinforcement is done, to connect projects sooner.
For a site that uses most of what it generates, a limit can beat a reinforcement bill. The ENA's 2025 guide adds that G100 devices for G99's small-installation procedures now need to be Fully Type Tested. The acceptable level is the DNO's call, so raise it early.
G99 timescales and your sales cycle
Published standards and deadlines for individual stages, not a connection date: reinforcement or a transmission assessment can add far more. Check your DNO's current timescales.
| Stage | Timescale | Source |
|---|---|---|
| Budget estimate (DNO doing all the work) | 10 working days | ENA guide |
| Quotation, non-contestable work only (SLC15) | 30 working days LV · 50 HV · 3 months EHV | ENA guide |
| Quotation, DNO doing all the work (Electricity Act s16) | 45 working days LV · 65 HV and EHV | ENA guide |
| Accepting a connection offer | Set in the offer, typically 30–90 days | ENA guide |
| Notice before witnessed commissioning | At least 15 days | ENA guide |
| Installation Document | Within 28 days of commissioning | ENA guide |
| Draft PGMD (Types B–D) | At least 28 days before first synchronising | NGED |
| Fast track (Form A1-2) | Response within 10 working days | SSEN (aim), NGED |
So the connection runs alongside the sale, not after it:
- raise G99 at the first meeting, so a wait or charge isn't a surprise;
- check capacity maps, and get a budget estimate on larger jobs;
- make the proposal conditional on the connection offer;
- time the customer's decision to the offer's acceptance window.
Why G99 applications stall
- Incomplete applications. The ENA guide asks for as much information as possible so the DNO can assess promptly. Gaps mean questions and delay.
- No compliance evidence. Inverters not on Connect Direct need a Compliance Verification Report and possibly site tests. Check Product IDs at design stage.
- Reinforcement. If the network can't take the connection, reinforcement may be needed, which the ENA guide warns could be prohibitively expensive.
- Interactive applications and transmission impact. Other projects nearby can make applications interactive, and some need an Evaluation of Transmission Impact from NESO.
- Lapsed offers. An offer not accepted in time expires, with no guarantee of the same terms again.
- The wrong route. Fast-track forms need every condition met; NGED says an SGI-3 application failing its network study becomes a full G99 enquiry.
How G99 fits into winning commercial work
To the customer, the grid connection is part of the purchase. An installer who explains G99 at the survey and submits a complete application looks more credible than one who finds a constraint weeks after the proposal.
That conversation belongs in a survey with the decision-maker present. If filling the diary with those is the bottleneck, our guide to how to get commercial solar leads compares the channels, and solar leads UK explains booked surveys vs form fills.
Solar Surveys UK lists booked commercial solar survey appointments for installers, qualified by phone with the decision-maker, roof ownership, energy consumption and intent confirmed. It's pay per appointment, priced by system size (see how much commercial solar leads cost), and no sit, no pay: if the customer doesn't sit for the survey, you don't pay. See the commercial solar leads we list or how solar survey leads work.
G99 for commercial solar: FAQ
Does a commercial solar system need a G99 application?
Almost always. G98 only covers Fully Type Tested generation up to 16A per phase at a premises (11.04kW three-phase). Anything larger comes under G99 and must be applied for before installation.
What is the difference between G98 and G99?
G98 covers small, Fully Type Tested micro-generation and, at a single premises, is fit and inform. G99 covers all other generation: apply first, accept a connection offer, then commission and submit the Installation Document.
Who submits the G99 application?
The ENA's guide expects the installer to submit it on the customer's behalf. SSEN asks for a letter of authority where the applicant isn't the landowner or occupier.
How long does a G99 application take?
It depends on the DNO, the voltage and the network. Licence standards for an LV generation quote are 30 working days (non-contestable work only) or 45 (DNO doing all the work), per the ENA guide, but reinforcement or a transmission assessment can add much more. Check your DNO's current timescales.
Does a G99 application cost money?
There may be a connection charge, feasibility study fees and assessment and design fees, which DNOs may charge since April 2018 but apply differently. SSEN, for example, doesn't charge to prepare quotes up to 50kW. Check your DNO's charging statement.
Which G99 form do I use?
For Type A under 50kW three-phase (17kW single-phase), the simplified form often called A1-1. Above that, the ENA standard application form. Check your DNO's own versions and portal.
What is G100 export limitation?
EREC G100 sets the rules for customer export limiting schemes. Capping export can let a system connect where the network can't take full export, and is part of the small-system fast track.
Is this legal or engineering advice?
No. It's a plain-English summary of the official sources below, checked on 6 October 2026. Rules and timescales change and each DNO applies them its own way, so confirm with the network operator and a competent electrical engineer.
Sources
Checked 6 Oct 2026. Official documents from the Energy Networks Association and distribution network operators. Where a rule or figure is one DNO's own, the text says so.
- Energy Networks Association — Distributed Generation Connection Guide: G98 & G99, Version 2.0, March 2025 (copy published by SSEN)
- Energy Networks Association — EREC G99 Form A1-2, application for Integrated Micro Generation and Storage installations (copy published by SSEN)
- National Grid Electricity Distribution — G99 Connection Procedures Guidance Document (January 2023)
- SSEN — G99 Fast Track Process
- SSEN — Generation connections (quote options and what to submit)
- SSEN — G98/G99 generator requirement documents (application and commissioning forms)
- SSEN — Microgeneration connections
Related guides
- All commercial solar lead guides
Every guide for UK installers buying commercial solar leads.
- Commercial solar survey checklist
What to confirm before, during and after the site visit.
- How to get commercial solar leads
Nine channels compared, and how to judge any lead provider.
- How to sell commercial solar
From booked survey to signed contract: process, proposal, objections.
- Solar leads UK: booked surveys, not form fills
What separates a good solar lead from an expensive one.
- How much do commercial solar leads cost?
Pricing by system size, the maths on a lead and a buyer's checklist.
- How solar survey leads work
What a solar survey is and how Solar Surveys UK works.
- Commercial solar leads in Manchester
Survey leads across Greater Manchester and the North West.
- Commercial solar leads in London
Survey leads across London and the South East.
- Commercial solar leads in Birmingham
Survey leads across Birmingham and the West Midlands.
- MCS certification for solar installers
How to get and keep MCS: standards, certification bodies, consumer codes, costs.
- G98 explained for installers
The 16A-per-phase limit, notify vs apply, the forms, and when you need G99.
- DNO application for solar
Find your DNO, pick the right route (G98, G99, G100) and get connected.
- Solar design software for UK installers
Easy-PV, OpenSolar, PV*SOL, PVsyst, Aurora and more, compared for UK work.
- UK solar wholesalers and distributors
Trade suppliers of panels, inverters, batteries and mounting, and how to choose one.
- MIS 3002 explained for solar PV installers
The MCS solar PV standard: scope, performance estimates, design, commissioning and handover.
- How to become a solar installer in the UK
Qualifications, training routes, MCS and the step to running your own solar business.
- SEO for solar companies
How UK installers win commercial solar enquiries from Google: pages, Google Business Profile, reviews, links and what it really takes.
- Solar advertising: Google and Facebook ads
Running Google, Meta and LinkedIn ads for commercial solar enquiries: targeting, landing pages, ad rules and what it really takes.
- Solar partnerships and referrals
Winning commercial solar work through energy brokers, landlords, contractors and customer referrals, and what it really takes.
- UK solar lead companies compared
Eight suppliers side by side: lead type, pricing, contracts and commercial vs residential.