G99 Application Checklist for Commercial Solar (Free, Printable)

The short answer

A commercial solar job above 16A per phase (11.04kW three-phase) needs a G99 application before you install. Check the threshold, find the DNO from the MPAN and gather the site data; apply on Form A1-1 (under 50kW three-phase) or the ENA Standard Application Form; get and accept the DNO's connection offer in time; then commission, with witness testing if the offer asks for it, and send Form A3-1 within 28 days. Tick off the 24 steps below, or print them.

Checked 25 Oct 2026 against ENA, NGED, SSEN and Ofgem documents. Ticks stay on this screen only; nothing is saved.

1. Before you apply

  • G98 limit explained →When a job needs G99 →

  • MPAN and DNO lookup →ENA: find my network operator

  • Capacity maps →ENA guide

  • ENA Standard Application Form

  • SAF (SSEN copy)NGED procedures

  • Commercial solar survey checklist →

  • ENA Connect DirectCompliance forms →

  • G100 export limitation guide →NGED export limitation

2. The application

  • Which G99 form →NGED formsSSEN forms

  • SAF (SSEN copy)

  • SSEN letter of authorityNGED procedures

  • What to gather →

3. DNO assessment and offer

  • SSEN quote optionsENA guide

  • G99 timescales →

  • ENA guideSSEN charges

  • ENA guide

4. Acceptance and installation

  • NGED procedures

  • ENA guide

  • ENA guide

5. Witness testing, commissioning and Form A3-1

  • NGED witnessing

  • EREC G99 (ENA)Distribution Code

  • SSEN commissioning formsENA guide

  • Ofgem: SEGMCS guide →

  • ENA guide

Free to share with your team, a customer or a forum thread. To link to it from your site, copy this:

<a href="https://solarsurveys.uk/guides/g99-application-checklist">G99 application checklist for commercial solar</a>

For the detail behind each step, see the G99 application guide, the DNO application guide and G98 explained.

G99 checklist: FAQ

Who submits and signs a G99 application?

The ENA's connection guide expects the installer to submit the application on the customer's behalf. NGED accepts agents working for the customer with their consent, and SSEN asks for a letter of authority where the applicant isn't the landowner or occupier. The customer signs the letter of acceptance on the DNO's offer, and the installer signs the declaration on the Installation Document (Form A3-1) after commissioning.

Is there a fee for a G99 application?

It depends on the DNO. The ENA guide says DNOs have been allowed to charge Assessment and Design fees since April 2018, whether or not the offer is accepted, and apply them differently. SSEN says it doesn't charge to prepare quotes up to 50kW, though connection costs may still apply. Feasibility studies are charged for, and NGED charges for witness testing. Check your DNO's charging statement.

How long does a DNO take to quote for a G99 connection?

The licence standards in the ENA guide are 30 working days at LV for non-contestable work only, and 45 working days at LV when the DNO does all the work (50 and 65 at HV). Reinforcement or a transmission assessment can add more, so check your DNO.

When is G99 Form A3-1 due?

Within 28 days of commissioning, per the ENA guide, with Form A2-4 if the interface protection isn't type tested. If the DNO witnesses the tests, the forms can be handed to its engineer on the day.

Sources

Opened on 25 Oct 2026. Where a rule is one DNO's own, the checklist names the DNO. The ENA's own pages for EREC G99, the Standard Application Form, Connect Direct and EREC G100 are linked as given in the ENA guide; always download forms from the DNO you are applying to. This is a summary, not legal or engineering advice.